A concrete sleeper retaining wall is built by setting steel posts in concrete footings, sliding concrete sleepers in between them, then putting drainage and backfill in behind. The face is the bit you look at. Whether it stays straight comes down to the parts you never see again: the set-out, the post holes, and what's behind the sleepers. Here's the build in the order it happens on a typical Melbourne block.
What a concrete sleeper retaining wall is
It's a row of steel posts concreted into the ground, with concrete sleepers stacked between them to hold back soil. The posts take the load and the sleepers span from post to post to form the face.
The in-between posts are usually galvanised H-section steel, so each sleeper end slides down into the channel of the post either side. End posts are usually C-shaped channel. The sleepers sit in the posts without fixings through them, which gives you a straight run as long as the posts are set right. If the posts are out, the whole line shows it.
Concrete sleepers don't rot the way timber can, which is why they suit most boundary walls, garden levels and walls beside driveways. Height, soil and whatever sits above the wall still decide how each one is built. For lower garden walls, raised beds and edging, timber sleepers on steel posts are still a good option where a softer look suits the garden.
Every wall ANKERMANN Landscape builds gets drainage behind it, and you'll see why further down. The wall types we build are on our retaining walls page.
Set-out, levels and checking boundaries and services
The job starts on the ground with a tape and a level: checking heights against the house, the boundaries and the rest of the yard, then marking out the wall line and finished levels. Get this wrong and every step after it is wrong too.
The finished height of the wall decides how much flat ground you get on top, where steps land, and how the yard meets door thresholds, paths and the garage entry. It also decides which way water runs once it's all finished.
Before a machine goes anywhere near the wall line, the services get located. Stormwater, sewer, water, gas and power can all run close to where you want the wall. Any question about exactly where the boundary is should be settled now too, not once the posts are in.
This is also where height and load come up. Engineering and permits depend on how high the wall is, what it's holding back and how close it sits to boundaries, driveways or buildings. Taller walls and walls carrying extra load, like a driveway, shed or deck above, often need engineering, and some need a permit. We flag this early. Check with your council, and we'll confirm what applies to your job before the scope is locked in.
Dig-out, post holes and concreting the posts
Next the crew digs along the wall line, cuts the bank back far enough to fit the drainage and backfill, then digs or augers the post holes and concretes the posts in. How deep and how far apart the posts go depends on the height, the soil, the load and any engineering, so there's no single right number.
The dig-out is usually wider than people expect. The gravel, geofabric and ag pipe all need room behind the sleepers, so the bank gets cut back past the wall line. On a tight block, that turns access and spoil into a real part of the job. Can a small machine fit down the side? Where does the spoil sit while the work goes on, and how does it get off site? We talk that through before the scope is set.
Each post is stood in its hole, checked for line, level and spacing against the set-out, and held there while the concrete goes in. Once the concrete sets, a post can't be nudged back into line. A post slightly out of plumb, or a footing that's too light for what's behind it, won't show on a new wall. It shows later, after a few wet spells with heavy soil leaning on it.
People often ask how deep the posts should go. It depends on the retained height, what sits above, the soil and any engineering, so don't copy the numbers off someone else's wall. We'll confirm the post depth and spacing for yours.
Sleepers in, then the drainage behind them
Once the post footings have set, the sleepers go in course by course and the drainage goes in behind them: ag pipe at the base, clean gravel backfill, geofabric, and the water taken to a suitable outlet. It's the part most likely to be skimped on and the part that matters most.
After rain, the soil behind a wall gets heavy and wet, and that pressure has to go somewhere. If the water can't get out, it pushes on the sleepers and posts. Water behind a wall is one of the main reasons walls lean or fail. Drainage won't save a wall with undersized footings or one carrying more than it was built for, but without it even a well-built wall is fighting the water. Our guide on why retaining walls fail goes into this in more detail.
What goes behind a typical wall:
- Ag pipe along the base, to collect water and carry it away.
- Clean gravel behind the sleepers, so water drains down to the pipe instead of sitting in the soil.
- Geofabric between the soil and the gravel, so fine soil doesn't wash in and clog the drainage over time.
- An outlet where the ag pipe actually discharges, so the water leaves the wall area.
The outlet is the bit people forget. An ag pipe that runs to nowhere just shifts the water along the back of the wall. Where it can go depends on the site, how much water comes down the slope and what's already there. It's not a case of pointing the pipe at the street and hoping. Where a new connection into stormwater is needed, a plumber looks after that part.
If the yard has bigger water problems, like pooling, downpipes with nowhere to go, or water running towards the house, it makes sense to sort them at the same time with drainage and site preparation work.
Backfill and compaction in layers
Behind the drainage gravel, soil goes back in layers rather than being dumped in all at once. Placed and compacted this way, the ground above the wall is far less likely to sink later.
Loose fill settles. Backfill a bank in one hit and the top can drop over time, leaving low spots right behind the sleepers. That's the worst place for water to collect, and it means the surface is working against the drainage underneath it.
Heavy compaction right behind new sleepers can push them out of line, so there's no heavy compacting close to the wall. How close you can go depends on the wall height and the engineering or supplier details for the backfill. The geofabric stays between soil and gravel the whole way up, so the drainage still works once the bank is full.
Finishing: capping and tying in paths, paving or garden beds
The last stage is levelling the ground above and below the wall and tying it into whatever comes next: garden beds, paving, a concrete path or a driveway. Some walls also get capping along the top for a cleaner edge.
Capping is mostly about looks, but decide on it early so the post heights suit it. The tie-ins matter more. Walls often sit right beside paths, steps or exposed aggregate driveways, and that join is where a mismatched level or a low spot shows up first. Plan the wall and the surface together and the edges line up. Set the falls on any new surface beside the wall to carry water away from the wall and the house, never towards them.
If you're still choosing what goes next to the wall, exposed aggregate has good grip underfoot (the sealer and finish make a difference), while pavers have more character than plain concrete. Our comparison of exposed aggregate, plain concrete and pavers covers the trade-offs. If new beds are going in above or below, drip irrigation is easiest to plan while the beds and levels are being set up.
On a new build, the wall is usually one part of a bigger order of works. Our guide to landscaping a knockdown-rebuild block covers how site clean-up, levels and drainage fit around it.
What to ask before work starts
Ask how the wall is held up, where the water goes, and how the job fits around the rest of the block. Whoever builds it should be able to answer each one plainly.
- Where will the water go? Ask what's going behind the sleepers and where the ag pipe discharges. "We'll sort the drainage" isn't an answer.
- How are post depth and spacing decided? You want to hear height, soil and load, plus engineering where it's needed.
- Does this wall need engineering or a permit? It depends on height, what sits above and how close the wall is to boundaries, driveways or buildings. We'll confirm what applies to your job, and it's worth checking with your council too.
- How does the machine get in, and where does the spoil go? On tight blocks this can change the whole approach.
- What happens next to the wall? If a path, driveway, paving or deck is going in alongside, ask how the levels and any extra load tie in.
Quotes are free and start from photos: shots from above, below and along the wall line, a rough length and height, and anything nearby like downpipes, trees, driveways or the boundary. You can send them through our contact page. If we need to come out for an on-site assessment, that may be charged depending on project location and scope.